Subcontractor bills
Bill work done against a work order, certify it, and pay it with retention and TDS.
Who does this: Quantity surveyor Project manager Accountant
- Open Subcontractor bills and choose New bill against a work order.
- Enter quantities done this period. Core shows the cumulative quantity and stops billing beyond the work order.
- Deductions are worked out: retention, TDS, advance recovery, and material issued beyond the allowance.
- Submit for certification. The project manager certifies.
- On certification, the bill posts to the books. Accounts pays it under payments or in a payment run.
Retention held is released at the end of the defect liability period from retention.