Plan which checks each kind of work needs, and record material test results.

Who does this: Project manager Site engineer

Inspection and test plans#

An ITP lists, for a kind of work, each check, how often, the acceptance criteria and who signs. Prepare it under Inspection plans; someone else approves it. Inspections then follow it.

Material tests#

Record tests (cube strength at 7 and 28 days, slump, steel tensile) under Material tests, with the sample, the lab and the result. A failed result raises a non-conformance. Material in quality hold is released when its test passes.