Material consumption and norms
Compare material used with what the work should have needed.
Who does this: Project manager Quantity surveyor Head of stores
Set norms: how much of each material one unit of work needs, for example 0.4 bags of cement per square metre of plaster. Core then compares, for each project and period, material issued with the theoretical quantity from approved progress. Differences beyond your tolerance appear in project health and the daily findings.
Work orders can carry a material allowance for the subcontractor; issues beyond it can be recovered on their bill.