CoreConstruction operating system

The daily report on the phone

Write the daily progress report from site with quantities, labour and photos.

Who does this: Site engineer

  1. Open the Progress tab and tap New report.
  2. Choose the site; today's date is filled in.
  3. For each BOQ item worked on today, enter the quantity. The quantity done so far and remaining is shown under each item.
  4. Add labour numbers, machinery, hindrances and photos.
  5. Tap Submit. It goes to the project manager.

If you saved a draft earlier, open it from the tab to continue. See daily progress reports.