The daily report on the phone
Write the daily progress report from site with quantities, labour and photos.
Who does this: Site engineer
- Open the Progress tab and tap New report.
- Choose the site; today's date is filled in.
- For each BOQ item worked on today, enter the quantity. The quantity done so far and remaining is shown under each item.
- Add labour numbers, machinery, hindrances and photos.
- Tap Submit. It goes to the project manager.
If you saved a draft earlier, open it from the tab to continue. See daily progress reports.