CoreConstruction operating system

The measurement book

Measure work on site, have it certified, and make it ready to bill.

Who does this: Quantity surveyor Project manager

Measurements are the agreed quantities you bill the client for. They usually trail daily progress, because they are taken jointly with the client's engineer.

Recording measurements#

  1. Open Measurements, choose the project and New measurement.
  2. For each BOQ item, add measurement lines: description, number, length, breadth, depth. Core works out the quantity.
  3. Attach the joint measurement sheet signed on site.
  4. Submit for certification.

Certifying#

The project manager checks and certifies. Certified quantities can go on the next client bill. Core stops measurements that would take an item past its BOQ quantity plus approved variations.