CoreConstruction operating system

Client running bills

Prepare running account bills from certified measurements, with GST, retention, TDS and advance recovery.

Who does this: Quantity surveyor Project manager Director

Preparing a bill#

  1. Open Client bills, choose the project and New bill.
  2. Core brings in every certified measurement not yet billed, at BOQ rates.
  3. Check the deductions, worked out from the project's terms:
    • Retention (for example 5%), released later. See retention.
    • Mobilisation advance recovery, at the agreed rate.
    • TDS the client will deduct.
    • Price escalation, if your contract has one. See price indices.
  4. GST is added from the project's GST registration and the client's state.
  5. Submit. The starter kit asks the project manager, then the director.

After approval#

The bill becomes an invoice in receivables. If e-invoicing applies, generate the IRN under TDS and e-invoices. Send the PDF to the client from the bill.

Withdrawing a bill#

If the client rejects a bill before it is paid, choose Cancel. Its measurements become free to go on the next bill. Once accounted, corrections go through a credit or debit note.