Daily progress reports
Record the day's work against the BOQ, with labour, machinery, photos and hindrances.
Who does this: Site engineer Project manager · Web and phone
The daily progress report (DPR) is the site's diary. Once approved, its quantities count towards BOQ progress.
Writing the report#
- Open Daily progress and choose New report (on the phone: Progress tab).
- Choose the site and date. One report per site per day.
- Work done: pick BOQ items and enter the quantity done today. Core shows the quantity done so far and what is left.
- Labour: numbers by trade, your own and each subcontractor's.
- Machinery: what worked and for how long. Logged plant hours can fill this; see plant.
- Hindrances: anything that stopped work (rain, drawings not received, client's decision pending), with hours lost.
- Photos: add photos of the work. On the phone they upload when you have signal.
- Submit before the day ends. It goes to the project manager for approval.
Approving#
The project manager checks the quantities against what they saw and approves. Quantities that would take an item past its BOQ quantity are flagged. See approving.
Correcting an approved report#
Approved reports cannot be edited, because progress and billing already used them. Add the correction on the next day's report with a note, or ask the project manager to send the report back if it was approved by mistake on the same day.