The bill of quantities (BOQ)
Load the BOQ, split it across sites, and watch progress against every item.
Who does this: Project manager Quantity surveyor
The BOQ is the list of work items in the client contract, each with a quantity, unit and rate. Everything that measures progress or bills the client counts against it.
Loading the BOQ#
The fastest way is Excel: download the BOQ template under Admin, Data import, fill it from the contract, and import it. See importing. You can also add items one by one under the project's BOQ tab.
Each item has: a code (as in the contract), description, unit, quantity, rate, and optionally a group (for example Substructure).
Splitting across sites#
If a project has several sites, split each item's quantity across them, for example 60% Tower A and 40% Tower B. Daily reports from each site then count against their share.
Watching progress#
The BOQ tab shows for each item: quantity, done to date (from approved daily reports), measured (from certified measurements), billed to the client, and what is left. Items close to or over their quantity are highlighted.
Changes to the BOQ#
Changes the client agrees go through a variation, which updates the BOQ and the contract value when approved. Do not edit quantities directly once work has started; the history matters for billing disputes.