Inspections and non-conformances
Inspect work with checklists, raise non-conformances, fix them and have someone else close them.
Who does this: Site engineer Project manager · Web
- Open Quality and choose New inspection.
- Choose the checklist (for example Slab before concreting), the location and the BOQ item.
- Answer each point: OK, not OK, or not applicable, with photos.
- Any not OK point can raise a non-conformance (NCR) with who should fix it and by when.
- The person fixes it and records the corrective action with a photo.
- Someone else (usually the project manager) verifies and closes it. You cannot close your own.
Open NCRs count against the project in project health.