CoreConstruction operating system

Inspections and non-conformances

Inspect work with checklists, raise non-conformances, fix them and have someone else close them.

Who does this: Site engineer Project manager · Web

  1. Open Quality and choose New inspection.
  2. Choose the checklist (for example Slab before concreting), the location and the BOQ item.
  3. Answer each point: OK, not OK, or not applicable, with photos.
  4. Any not OK point can raise a non-conformance (NCR) with who should fix it and by when.
  5. The person fixes it and records the corrective action with a photo.
  6. Someone else (usually the project manager) verifies and closes it. You cannot close your own.

Open NCRs count against the project in project health.